logo

This Product is Licensed to ,

Change Font Style & Size  Show / Hide

24

  •            

 
CDJ 2026 MHC 338 print Preview print Next print
Court : High Court of Judicature at Madras
Case No : Arbitration O.P.(Com.Div.). No. 602 of 2022
Judges: THE HONOURABLE MR. JUSTICE N. ANAND VENKATESH
Parties : M/s. Muthu Construction - Salem, Rep.by its Proprietor Kannan, Namakkal Versus Union of India, Rep. by its Principal Chief Engineer, Southern Railway, through DEN/ W/Salem, Office of the Divisional Railway Manager, Salem
Appearing Advocates : For the Petitioner: Sharath Chandran, Advocate. For the Respondent: V.J. Latha, SCGSC.
Date of Judgment : 20-01-2026
Head Note :-
Arbitration and Conciliation Act, 1996 – Sections 18, 28(3), 34(2)(b), 34(2A) – Setting aside arbitral award – Patent illegality – Bias – Interpretation of contract terms – Majority arbitral award rejecting contractor’s claim regarding measurement and payment based on “per track metre” set aside – Arbitral Tribunal adopted a different yardstick for certain items by relying on an alleged “mutual understanding” instead of the express terms of the contract.

Court Held – Petition Allowed – Ignoring clear contractual terms and substituting them with presumed understanding constitutes patent illegality under Section 34(2A) – Dissenting arbitrator also alleged bias and preconceived conclusions by majority members, indicating violation of principles of natural justice and Section 18 of the Act – Bias vitiates the arbitral process and strikes at the fundamental policy of Indian law – Majority award therefore liable to be set aside with costs of Rs.1,50,000/- awarded to the petitioner.

[Paras 11, 14, 16, 20, 21]

Cases Cited:
State of Chhattisgarh v. SAL Udyog (P) Ltd., (2022) 2 SCC 275
Delhi Airport Metro Express (P) Ltd. v. Delhi Metro Rail Corporation Ltd., (2022) 1 SCC 131
Central Organization for Railway Electrification v. ECI SPIC SMO MCML (JV), 2025 1 MLJ 289

Keywords: Arbitral Award – Patent Illegality – Bias in Arbitration – Natural Justice – Section 34 Arbitration Act – Contract Interpretation – Railway Contract – Majority vs Dissenting Arbitrator
Summary :-
1. Statutes / Acts / Rules / Orders / Regulations, and Sections Mentioned:
- Arbitration and Conciliation Act, 1996
- Section 34 of the Arbitration and Conciliation Act, 1996
- Section 34(2)(i)(b) of the Act
- Section 34(2A) of the Act
- Section 34(2‑A) of the Act
- Section 18 of the Act
- Section 28(3) of the 1996 Act

2. Catch Words:
Arbitration, bias, natural justice, patent illegality, interpretation, award, set aside, contract, majority award, dissenting arbitrator, principle of nemo judex, procedural fairness.

3. Summary:
The petition under Section 34 of the Arbitration and Conciliation Act challenges the majority award dated 25‑02‑2022. The petitioner contends that the award is vitiated by bias and suffers from patent illegality in its interpretation of “per track metre”. The Court examined the award’s reasoning, finding that the tribunal ignored clear contractual language and adopted a non‑possible view, amounting to patent illegality. The dissenting arbitrator’s allegation of bias against the majority members was also considered, and the Court held that such bias taints the award. Relying on precedents, the Court concluded that the award must be set aside. Consequently, the petition is allowed with costs awarded to the petitioner.

4. Conclusion:
Petition Allowed
Judgment :-

(Prayer: PETITION under Section 34 of the Arbitration and Conciliation Act, 1996 praying to set aside the Arbitral Award dated 25.2.2022 passed by the majority of the Arbitral Tribunal in the matter of SSE/ PW/CTR-CBF and SSE/PW/E/PTJ Sections-Contract Agreement No.SA/ 280 dated 06.2.2019, to the extent it rejects Claim No.4 and to direct the respondent to pay the costs.)

1. In this petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 (for short, the Act), the petitioner assails the majority award dated 25.2.2022 passed by the Arbitral Tribunal.

2. Heard both.

3. The facts leading to filing of this case are as follows:

                     (i) The petitioner is a proprietary concern, which entered into a contract with the respondent titled as repairs to the existing dily changing corroded fittings over points and crossings/SEJs/bridges/ curves, boxing and tidying of ballast, painting of boards, etc. Two contracts were entered into namely SA/279 and SA/280. This case pertains to SA/280.

                     (ii) The petitioner participated in the tender that was floated by the respondent and was declared as the successful bidder, pursuant to which, they were awarded the contract. The letter of acceptance 27.11.2018 for a value of Rs.2,76,83,452/- was also issued to them.

                     (iii) The claims made by the petitioner before the Arbitral Tribunal pertained to earnest money deposit, security deposit, final bill amount and payment for the difference as per the unit of measurement of “track metre”. It was an admitted case that the only issue, which became the subject matter of adjudication before the Arbitral Tribunal, was with regard to the last component namely payment for the difference as per the unit of measurement of “track metre”.

                     (iv) Ultimately, the majority of the Arbitral Tribunal came to the conclusion that the claim made by the petitioner under this head was found to be untenable and hence, it came to be rejected. Aggrieved by the majority award, the above petition has been filed before this Court.

4. The learned counsel for the petitioner questioned the majority award mainly on two grounds and they are:

                     (a) that it is vitiated by bias, that it violates Section 18 of the Act and the principles of natural justice and that therefore, it is liable to be interfered under Section 34(2)(i)(b) of the Act; and

                     (b) that the interpretation given by the majority of the Arbitral Tribunal to deny the claim made by the petitioner suffers from patent illegality and hence, it is liable to be interfered under Section 34(2A) of the Act.

5. Per contra, the learned Senior Central Government Standing Counsel appearing for the respondent submitted that the dissenting note of one of the Arbitrators cannot automatically result in attributing bias as against the remaining members of the Arbitral Tribunal, that the majority of the Arbitral Tribunal has rightly interpreted the relevant clause in the agreement, that it is a possible view taken by the Arbitral Tribunal and that it cannot be interfered by this Court while exercising its jurisdiction under Section 34 of the Act.

6. This Court has carefully considered the submissions of the learned counsel on either side and perused the materials available on record and more particularly the impugned award.

7. This Court will first deal with the second issue raised with respect to the interpretation of the expression “per track metre” and test as to whether the view taken by the majority of the Arbitral Tribunal is a possible view.

8. The sum and substance of the contention raised on the side of the petitioner is that Schedule B in the agreement consisted of six categories of works, which used the expression “per track metre” as the unit of measurement. Except with respect to item Nos.1 and 2, for all the other items, the measurements were taken separately for each track whereas in so far as item Nos.1 and 2 were concerned, they were treated differently and the measurements were recorded by clubbing two tracks (up and down) and it has been questioned by the petitioner on the ground that these two items could not be treated/ measured differently especially when the unit of measurement was one and the same.

9. For proper appreciation, item Nos.1 and 2 in Schedule B are extracted as hereunder:

S.No .Description of WorkQuantityUnitRateAmount
1Boxing and tidying of ballast duly cleaning and uprooting bushes all vegetation available over the ballast and 60 cm from edge of ballast and cutting of other bushes grown above cess level on either side of track on the cess including de-weeding of vegetation/bushes in between track and on the cess including labours and tools, etc. complete and as directed by the engineer in charge at site (in parallel track) (Both up & down line) i. SSE/PW/TUP21630Per track metreRs.48/-Rs.10,38,240/-
2................................................ Charge at site (in parallel track) (Both up & down line) ii. SSE/PW/ED.81270Per track metreRs.48/-Rs.39,00,960/-
10. The majority of the Arbitral Tribunal rendered a finding that the schedule could have been better drafted to avoid any ambiguity in the interpretation. However, the majority of the Arbitral Tribunal also rendered a rather curious finding that there was a mutual understanding between the parties that in so far as item Nos.1 and 2 were concerned, the same was understood by both parties that the measurement would be made by clubbing two tracks (up & down). In short, when the respondent was attempting to give a different interpretation for item Nos.1 and 2 with respect to the yardstick for computation and payment, the majority of the Arbitral Tribunal, without assigning any reason to justify such a stand taken by the respondent, adopted a different yardstick for item Nos.1 and 2 for the very same unit of measurement.

11. That apart, the majority of the Arbitral Tribunal, by casting aside the actual wordings in the contract, replaced them with the supposed mutual understanding between the parties and such a construction made by the majority of the Arbitral Tribunal, when the terms of the contract were clear and unambiguous, suffers from patent illegality.

12. Useful reference can be made to the judgment of the Hon’ble Apex Court in State of Chhattisgarh Vs. SAL Udyog (P) Ltd. [reported in 2022 (2) SCC 275] wherein the relevant portion is extracted as hereunder:

                     “26. To sum up, existence of Clause 6(b) in the agreement governing the parties, has not been disputed, nor has the application of the Circular dated 27-7-1987 issued by the Government of Madhya Pradesh regarding imposition of 10% supervision charges and adding the same to cost of the Sal seeds, after deducting the actual expenditure been questioned by the respondent Company. We are, therefore, of the view that failure on the part of the learned sole arbitrator to decide in accordance with the terms of the contract governing the parties, would certainly attract the “patent illegality ground”, as the said oversight amounts to gross contravention of Section 28(3) of the 1996 Act, that enjoins the Arbitral Tribunal to take into account the terms of the contract while making an award. The said “patent illegality” is not only apparent on the face of the award, it goes to the very root of the matter and deserves interference. Accordingly, the present appeal is partly allowed and the impugned award, insofar as it has permitted deduction of “supervision charges” recovered from the respondent Company by the appellant State as a part of the expenditure incurred by it while calculating the price of the Sal seeds, is quashed and set aside, being in direct conflict with the the relevant circular. The impugned judgment dated 21-10-2009 is modified to the aforesaid extent.”

13. Further reference can be made to the decision of the Hon’ble Apex Court in Delhi Airport Metro Express (P) Ltd. Vs. Delhi Metro Rail Corporation Ltd. [2022 (1) SCC 131] wherein the relevant portion is extracted as hereunder:

                     “29. ............. The permissible grounds for interference with a domestic award under Section 34(2-A) on the ground of patent illegality is when the arbitrator takes a view which is not even a possible one, or interprets a clause in the contract in such a manner which no fair-minded or reasonable person would, or if the arbitrator commits an error of jurisdiction by wandering outside the contract and dealing with matters not allotted to them. An arbitral award stating no reasons for its findings would make itself susceptible to challenge on this account. The conclusions of the arbitrator which are based on no evidence or have been arrived at by ignoring vital evidence are perverse and can be set aside on the ground of patent illegality. Also, consideration of documents which are not supplied to the other party is a facet of perversity falling within the expression ‘patent illegality’.”

14. The interpretation given by the majority of the Arbitral Tribunal is certainly not a possible view as it has actually wandered outside the contract by ignoring the specific terms of the contract, which would render the findings perverse and they would have to be set aside on the ground of patent illegality. In view of the same, this Court finds that the majority of the Arbitral Tribunal ought to have adopted the same yardstick for item Nos.1 and 2 like it was done for the other items where the measurements were recorded separately for each track and the amount was computed.

15. In so far as the first issue regarding bias is concerned, the dissenting Arbitrator made the following observations:

                     “1. In para 10.7 of the arbitral award, Shri Neeraj Jain, the learned Presiding Arbitrator and Ms.Aradhana Chak, the learned Co-Arbitrator have stated that-

                     ‘The Arbitrators place on record that the Presiding Arbitrator Neeraj Jain and Co-Arbitrator Ms.Aradhana Chak have both also acted as Co- Arbitrators in an almost similar case conducted almost concurrently pertaining to agreement SA/279 dt. 06/02/2019 where the issues are similar and the award has been declared recently.’

                     ………

                     For the reasons mentioned above, my both the learned colleague arbitrators did not discuss this case with me with open mind and kept their preconceived conclusions and findings in this case too. Hence, my views were kept aside while writing the arbitral award.

                     ………….

                     (xi) Most of the above mentioned issues were deliberated in detail in the hearing held on 08.01.2022 and also figured in the order sheet of this hearing issued by the learned Presiding Arbitrator under his signature as Arbitration Notification No.7 vide communication No.NJ/Arb/ SR/Muthu/12 dt. 10.01.2022. Surprisingly the same have been kept aside by Shri Neeraj Jain, the learned Presiding Arbitrator and Ms.Aradhna Chak, the learned Co-Arbitrator while drawing the conclusions, finding facts and deciding the arbitral award.”

16. A Court, which deals with an award rendered by majority of the Members, need not apply its mind on the findings rendered by the dissenting Arbitrator. This is in view of the fact that the majority award becomes the actual award that governs the particular dispute. However, there is one exception to this rule where the dissenting Member alleges bias against the majority Members. This issue has to be certainly considered by the Court since bias vitiates the award for violation of the principles of natural justice and it also goes against the fundamental policy of the Indian Law.

17. In the case on hand, the dissenting Arbitrator has gone on record and stated that his colleagues on the Tribunal were openly biased and had adjudicated the case with a preconceived notion and did not discuss the case with him.

18. At this juncture, it will be relevant to take note of the judgment of the Hon’ble Apex Court in Central Organization for Railway Electrification Vs. ECI SPIC SMO MCML (JV) [reported in 2025 1 MLJ 289] wherein the relevant portions read thus:

                     “76. The principles of natural justice principally consist of two rules: (i) no one shall be a judge in their own cause (nemo judex in causa sua); and (ii) no decision shall be given against a party without affording a reasonable opportunity of being heard [Express Newspaper (P) Ltd. v. Union of India, 1958 SCC OnLine SC 23 [95]; A K Kraipak v. Union of India, (1969) 2 SCC 262 [20]; Mohinder Singh Gill v. Chief Election Commissioner, (1978) 1 SCC 405 [52]; Swadeshi Cotton Mills v. Union of India, (1981) 1 SCC 664 [27]] Adherence to the principles of natural justice is a facet of procedural fairness. A decision made by the State to the prejudice of a person must be after following the basic rules of justice and fair play {State of Orissa v. Binapani Dei, 1967 SCC OnLine SC 15 [9]}. The principles of natural justice are applied because administrative or quasi-judicial proceedings can abridge or take away rights {Union of India v. K P Joseph, (1973) 1 SCC 194 [10]}. Application of the principles of natural justice prevents miscarriage of justice {A K Kraipak (supra) [20]}. Natural justice has both an intrinsic and an instrumental function. The intrinsic function values natural justice as an end in itself. It values natural justice as an essential feature of fairness. In its instrumental element, natural justice is viewed as a means to achieving just outcomes.

                     77. The principle of nemo judex is based on the precept that justice should not only be done but manifestly and undoubtedly be seen to be done The King v. Sussex Justices, [(1924) 1 KB 256]. The principle of nemo judex applies to judicial, quasi-judicial, and administrative proceedings J Mohapatra & Co. v. State of Orissa, {(1984) 4 SCC 103 [9]}. An adjudicator should be disinterested and unbiased {A K Roy v. Union of India, (1982) 1 SCC 271 [97]}. A bias is a predisposition to decide for or against one party, without proper regard to the true merits of the dispute {Government of TN v. Munuswamy Mudaliar, 1988 Supp SCC 651 [12]}.

                     ….…

                     88. The principle governing the doctrine of bias is that a member of a judicial body with a predisposition in favour of or against any party to a dispute or whose position in relation to the subject matter or a disputing party is such that a lack of impartiality would be assumed to exist should not be a part of a tribunal composed to decide the dispute Gullapalli Nageswara Rao v. State of AP {1959 SCC OnLine SC 53 [6]}; relied in Mineral Development Ltd. v. State of Bihar {1959 SCC OnLine SC 49 [10]}. This principle is applicable to authorities who have to act judicially in deciding rights and liabilities and bodies discharging quasi-judicial functions. A quasijudicial authority empowered to decide a dispute between opposing parties “must be one without bias towards one side or the other in the dispute.” {Gullapalli Nageswara Rao v. A P State Road Transport Corporation (supra)}. A member of a tribunal which is called upon to try issues in judicial or quasi-judicial proceedings must act impartially, objectively, and without bias {Manak Lal v. Dr. Prem Chand Sighvi {1957 SCC OnLine SC 10}.”

19. The above judgment of the Constitution Bench reiterated that the adherence to the principles of natural justice is a facet of procedural fairness, that bias is a pre-disposition to decide for or against one party without proper record to the true merits of the dispute and that this goes against the fundamental principle of doctrine of bias since the Members of the Arbitral Tribunal are expected to act impartially, objectively and without bias.

20. In the light of the above discussions, this Court also holds that the majority award passed by the Arbitral Tribunal is tainted by bias/premeditation. Hence, the principle of poisoning the well will apply and the award will be afflicted by bias. In view of the same, it violates Section 18 of the Act and it goes against the fundamental policy of the Indian Law under Section 34(2)(i)(b) of the Act.

21. The conspectus of the above discussions leads to the only conclusion that the impugned majority award is liable to be set aside on the ground of bias/premeditation.

22. Accordingly, the impugned majority award is set aside and the above original petition stands allowed with costs of Rs.1,50,000/- (Rupees one lakh and fifty thousand only) payable by the respondent to the petitioner.

 
  CDJLawJournal