logo

This Product is Licensed to ,

Change Font Style & Size  Show / Hide

24

  •            

 
CDJ 2026 MHC 2425 print Preview print print
Court : High Court of Judicature at Madras
Case No : Arb O.P(COM.DIV.) No. 810 of 2025
Judges: THE HONOURABLE MR. JUSTICE SENTHILKUMAR RAMAMOORTHY
Parties : Dodeja Electrical Engineers through its Proprietor, Tanuja Panjwani, New Delhi Versus Larsen & Toubro Limited Maharshtra
Appearing Advocates : For the Petitioner: Pranam Jain, Advocate. For the Respondent: S.R. Raghunathan, Advocate.
Date of Judgment : 26-03-2026
Head Note :-
The Arbitration & Conciliation Act - Section 11(6) -
Judgment :-

(Prayer: Petition filed under Section 11(6) of The Arbitration and Conciliation Act, 1996 praying to appoint a sole arbitrator to hear and adjudicate the disputes between the Petitioner and the Respondent arising out of the letter of Intent-LTCD/EXP/WC/LOI/ELE/SC/108 dated 26.10.2015 and along with work order No.E9044WOD7000277 as well as work order E90044WOD5000355 and direct the respondent to pay cost.)

1. Relying on clause 21 of the contract between the parties, the petitioner has applied for appointment of an arbitrator after issuing notice dated 22.11.2024 under Section 21 of the Arbitration and Conciliation Act, 1996 (The A & C Act).

2. Learned counsel for the petitioner invited my attention to the arbitration clause and to the Section 21 notice. He pointed out that such notice was replied to by the respondent on 14.01.2025 stating that the notice had been issued after the lapse of more than three years and that the cause of action does not survive.

3. Learned counsel for the respondent responded to these contentions by referring to the earlier suit filed by the petitioner before the District Judge, Commercial Court, Delhi in C.S.(Comm.) No.654 of 2024. Learned counsel points out that said suit was withdrawn by the petitioner herein/plaintiff therein without obtaining leave of the Commercial Court to initiate arbitral proceedings. Relying on Order XXIII Rule 1(3) and (4) of Code of Civil procedure, 1908, learned counsel submits that without obtaining leave, the petitioner is not entitled to initiate arbitral proceedings and that the filing of a civil suit tantamounts to giving a go-by to the arbitration clause. He has relied on the following judgments in support of the contention:

               (i) Magma Leasing Limited vs. NEPC Micon Limited and another (1997 SCC OnLine Cal 268)

               (ii)Raj & Associates vs. Videsh Sanchar Nigam Limited and others (2004 (76) DRJ 60)

4. According to learned counsel, the proposition laid down in both these judgments is that a party choosing to institute a civil suit in spite of an arbitration agreement does not have the option thereafter to seek a reference either under Section 8 of the statute or otherwise.

5. Considering the rival contentions, the question that falls for consideration is whether the request for appointment of an arbitrator should be declined in view of the defence raised by the respondent. The scope of Section 11 of A & C Act has been elucidated in multiple judgments, including judgments of the Supreme Court. In Vidya Drolia and Others Vs. Durga Trading Corporation [(2021) 2 SCC 1] (Vidya Drolia), the Supreme Court held that while considering such a petition, the Court should examine whether an arbitration agreement exists between the parties and whether the dispute is manifestly non-arbitrable. It was also held that refusal to refer should be limited to removal of dead wood. Both parties agree that Clause 21 provides for resolution of disputes by arbitration. For the sake of clarity, said clause is set out below:

               ‘21. ARBITRATION:

               All disputes and differences arising out of the connections(s) with this order failing amicable settlement shall be referred to Project Manager / Project Director of site and his decision will be final and binding on both parties.’

6. The principal ground on which the request for appointment of an arbitrator is resisted is the filing of a civil suit by the petitioner. Such civil suit was withdrawn by the petitioner after realising that there is an arbitration agreement in clause 21 of the agreement.

7. On the basis of statement made by the petitioner, the Court issued the following order:

               ‘03.10.2024

               Present – Sh.Piyush Upadyay, Ld. Counsel for plaintiff through VC

               It is submitted by Ld. Counsel for plaintiff that he has already made statement to withdraw the present suit on 28.09.2024.

               I have perused the record. Perusal of file reveals that Ld. Counsel for plaintiff has already made statement on 28.09.2024. In view of the statement made by Ld. Counsel the plaintiff, the present suit is dismissed as withdrawn. As the Ld. Counsel for plaintiff has withdrawn the suit at initial stage, I am of the view that the plaintiff is entitled to refund of court fees. Necessary certificate be issued. File be consigned to record room, after necessary compliance.’

8. While the agreement to resolve disputes by arbitration is prima facie enforceable, the Project Manager/Project Director cannot be the arbitrator as per applicable law. In my view, in the facts and circumstances outlined above, the request for appointment of an arbitrator cannot be refused on the basis of the defence raised by the respondent. Such pleas may be raised by the respondent before the Arbitral Tribunal.

9. Accordingly, Mr.V.Kuberan, Advocate, No.25, Bazulla Road, Jains Anjana, T.Nagar, Chennai – 600 017 (Mobile No.9840043486), is appointed as the Arbitrator to adjudicate the dispute. Learned Arbitrator is requested to enter upon reference. The fees and expenses may be fixed by the Arbitrator in consultation with the parties. All contentions, including contentions raised herein, are left open to be raised in course of arbitral proceedings.

10. This petition is disposed of on the above terms.

 
  CDJLawJournal