logo

This Product is Licensed to ,

Change Font Style & Size  Show / Hide

24

  •            

 
CDJ 2025 APHC 1879 print Preview print print
Court : High Court of Andhra Pradesh
Case No : Land Acquisition Appeal Suit No. 65 Of 2015
Judges: THE HONOURABLE MR. JUSTICE NINALA JAYASURYA & THE HONOURABLE MR. JUSTICE TUHIN KUMAR GEDELA
Parties : The Special Deputy Collector, T.G.P., Rapur Versus Nallavadla Mallikarjuna Reddy & Others
Appearing Advocates : For the Appellant: The Advocate General (AP). For the Respondents: Chetluru Sreenivas, M. Dasaradha Rami Reddy, Advocates.
Date of Judgment : 22-12-2025
Head Note :-
Land Acquisition Act, 1894 - Section 4 (1) -
Judgment :-

Ninala Jayasurya, J.

1) The State aggrieved by the Order dated 22.09.2014 in LAOP No.1 of 2011 on the file of the Court of the V Additional District Judge And Sessions Judge-Cum-Motor Accidents Claims Tribunal, Nellore, filed the present Appeal.

2) For better appreciation of the case, the parties are referred to as they are arrayed in the L.A.O.P.

3) Heard Mr.T.Vishnu Teja, learned Special Government Pleader, attached to the office of the learned Advocate General. Also heard Mr.K.G.Krishna Murthy, learned Senior Counsel appearing on behalf of the respondents and Mr.Chetluru Srinivas, learned counsel for the review petitioner in I.A.No.1 of 2023. Perused the material on record.

4) For the purpose of Kandaleru Project a Notification under Section 4 (1) of the Land Acquisition Act, 1894 (for short ―the Act‖) was issued on 01.05.2007. Subsequently, a Draft Declaration under Section 6 of the Act was published. Pursuant to the said Draft Notification, the structures and wells of the respondents / claimants situated in Gundavolu Village of Rapur Mandal were acquired. The Land Acquisition Officer after conducting enquiry, passed Award No.2/2009-10, dated 18.05.2009 determining the compensation / value of the structures etc., by taking into consideration its nature and the plinth area.

5) Aggrieved by the value / compensation fixed by the LAO, the respondents / claimants while receiving the same under protest, invoked Section 18 of the Act. Before the Reference Court on behalf of the respondents / claimants PWs 1 to 3 were examined and Exs.A1 and A2 were marked. On behalf of the Referring Officer, R.W.1 was examined and Ex.B1 i.e., Award dated 18.05.2009 was marked. The learned Reference Court vide order under appeal enhanced the market value of the structures per sq.mtr., by 150% over and above the market value fixed by the LAO. It had also granted the statutory benefits on the enhanced market value.

6) Mr.Vishnu Teja, learned counsel for the appellant made elaborate submissions contending that the order under appeal is unsustainable, contrary to law and liable to be set aside. He submits that the enhancement of market value by the Reference Court is highly excessive, without any valid basis and therefore liable to be interfered with. He also contends that the Reference Court on an erroneous appreciation of the matter went wrong in coming to a conclusion that the value fixed by the LAO for the structures is improper and arbitrary. He submits that the LAO determined the market value on the basis of the estimates prepared by the Engineering Wing of the Irrigation and Power Department, whereas the estimates (Ex.A1) relied on by the respondent / claimants were prepared by a private Civil Engineer, and the learned Reference Court has committed grievous error in relying on Ex.A1 for enhancement of the market value. He also contends that in Land Acquisition matters the Court is required to fix just and reasonable compensation, whereas in the present case, the Reference Court enhanced the Market Value of the structures by 150% over and above Market Value fixed by the LAO, without assigning any reasons and therefore, the said enhancement warrants interference by the Appellate Court.

7) The learned Special Government Pleader further submits that the LAO fixed the market value of the structures on the basis of estimates prepared by Engineering Wing of Irrigation and Power Department, the same were not filed along with the Award copy (Ex.B1). He submits that the said estimates are very much essential for arriving at just and reasonable compensation. Therefore, the same are filed as additional material in the connected appeal. He also contends that a bare perusal of Ex.A1 would disclose the irregularities / mischief committed by the private Engineer (PW2) in preparing the estimates. In the light of the additional evidence, and as the determination of the market value by the learned Reference Court by 150% per square meter over and above the market value fixed by the LAO is not sustainable, he urges for remand of the matter by duly setting aside the order under Appeal.

8) Per contra, Mr.K.G.Krishna Murthy, learned Senior Counsel appearing for the respondents / claimants strenuously contended that the order of Reference Court is valid and the conclusions recorded therein are arrived at on thorough appreciation of evidence on record and, therefore, the same warrants no interference by this Court. Referring to the relevant depositions of the witnesses and the documentary evidence available on record, the learned counsel would submit that the respondents in fact claimed 300% more over and above the market value fixed by the LAO, but the Reference Court enhanced the market value of the structures only 150% over and above the value fixed by the LAO. He submits that fixation of the market value on the basis of the estimates prepared by Engineering Wing of Irrigation and Power Department, which is filed as additional evidence is not correct as the same cannot be a valid basis for determination of the market value. In elaboration, he submits that the said estimates were prepared by the beneficiary Department, whereas as per the Government Orders in G.O.Ms.No.291, dated 05.08.1982, R&B Department was required to prepare estimates for determination of the market value. That apart, the learned Senior Counsel contends that even the said estimates which are sought to be received as additional evidence are very much available at the time of adjudication of the matter by the Reference Court and having failed to adduce evidence at the relevant point of time, the appellant cannot be permitted to refer to the same in a casual manner and the same cannot be looked into.

9) The learned Senior Counsel further contends that the present appeal was filed in the year 2015 and after long lapse of time, that too in the middle of the arguments, the Interlocutory Application seeking to receive the additional evidence was filed only in the other appeal and further that it is settled Law that such an application cannot be allowed unless the requirements stipulated in Order 41 Rule 27 (1) (aa) of CPC are fulfilled. He submits that no application is filed much less with an affidavit stating that the additional material / evidence was not within the knowledge of the deponent or that the same could not, even after exercise of due diligence, be produced at the time of consideration of the O.P., by the learned Reference Court. In essence, his contention is that as the estimates prepared by the Engineering Wing of Irrigation and Power Department are very much available with the LAO, therefore such evidence / material cannot be said to be not within the knowledge of the Department or that the same could not be produced after exercise of due diligence, at the time of examination of the claim for enhancement by the Reference Court. He, therefore, submits that reference to the additional material is of no avail to the appellant. He further contends that the appeal is devoid of merits and the market value enhanced by the Reference Court is just and reasonable. He urges for dismissal of the appeal.

10) In reply, the learned Government Pleader made submissions with reference to the decisions of the Hon’ble Supreme Court reported in Sanjay Kumar Singh Vs State of Jharkhand((2022) 7 SCC 247) ; Shalimar Chemical Works Ltd., Vs Surendra Oil and Dal Mills (Refineries) and Ors., ((2010) 8 SCC 423) and Malayalam Plantations Ltd., Vs State of Kerala and Another((2010) 13 SCC 487), and prays for allowing the appeal and to remand the matter for determination of the market value, afresh by the Reference Court.

11) On an appreciation of the rival contentions, the points that arise for adjudication by this Court are –

                  1) Whether the market value fixed by the Reference Court is not just, or reasonable, highly excessive, without valid basis and as such, the order under appeal is liable to be interfered with?

                  2) Whether a case is made out for remand as prayed for?

                  3) To what relief?

12) Before dealing with Point No.1, it is deemed appropriate to consider the contentions addressed by the learned counsel on both sides with reference to Point No.2 and answer the same.

Point No.2:

13) The basic facts with reference to the purpose of acquisition and the issuance of Section 4 (1) Notification dated 01.05.2007 and passing of Award dated 18.05.2009 (Ex.B1) are not in dispute. It is also not in dispute that against the order of the Reference Court dated 22.09.2014, the present appeal was preferred in the year 2015. More than 10 years have gone by and the application I.A.No.1 of 2025 to receive additional evidence was filed under Order 41 Rule 27 (1)(aa) of CPC on 21.01.2020 during the course of hearing. Be that as it may.

14) Order 41 of CPC deals with appeals from original decrees.

15) Order 41, Rule 27 of CPC deals with production of additional evidence in appellate Court. For ready reference, the same is extracted hereunder:

                  27. Production of additional evidence in Appellate Court.—(1) The parties to an appeal shall not be entitled to produce additional evidence, whether oral or documentary, in the Appellate Court. But if- (a) the Court from whose decree the appeal is preferred has refused to admit evidence which ought to have been admitted, or

                  (aa) the party seeking to produce additional evidence, establishes that notwithstanding the exercise of due diligence, such evidence was not within his knowledge or could not, after the exercise of due diligence, be produced by him at the time when the decree appealed against was passed, or

                  (b) the Appellate Court requires any document to be produced or any witness to be examined to enable it to pronounce judgment, or for any other substantial cause, the Appellate Court may allow such evidence or document to be produced, or witness to be examined.

                  (2) Wherever additional evidence is allowed to be produced by an Appellate Court, the Court shall record the reason for its admission.‖

16) A reading of the above extracted provision of law i.e., Rule 27(1)(aa), makes it clear that the party, who is seeking to produce additional evidence, has to establish that despite exercise of due diligence, such evidence was not within the knowledge or that the same could not, after the exercise of due diligence could not be produced by him, at the time when the decree appealed against was passed.

17) In the present case, it is not in dispute that the documents / estimates filed as additional material / evidence in the connected appeal are very much within the knowledge of the department / authorities i.e., LAO/Special Deputy Collector and it is not as if even after exercise of due diligence the said evidence was not within the knowledge of the appellant or that the same could not be produced after exercise of due diligence, much less that it was obtained after exercise of due diligence from the custody of the other department. It may be pertinent to mention here that in fact, in the order under challenge this aspect of not filing / exhibiting the estimates, which are prepared by the engineering team of Irrigation and Power Department, which is stated to be the basis for determination of Market Value by the LAO, non- examination of the Engineer who prepared the same were specifically discussed by the learned Reference Court. However, the appellant did not choose to file any application to receive the additional evidence along with appeal filed in the year 2015, much less a separate application in the present case, like in the connected appeal. Though no specific time limit is stipulated for filing application under Order 41 Rule 27 of CPC, the application to receive additional evidence, cannot be ordered, unless the Court is satisfied that the reasons / explanation for non-production of the evidence sought to be received is established in terms of Order 41 Rule 27(1)(aa) of CPC. In the case on hand, the question of the evidence i.e., the estimates prepared by the Irrigation and Power Department is not within the knowledge of the Department / appellant or that even after exercise of due diligence could not be produced before the Reference Court does not arise at all.

18) At this juncture, it is also relevant to refer to the decisions on which reliance is placed by the learned counsel for the appellant, in the connected appeal.

19) In Sanjay Kumar Singh’s case (referred to supra), the Hon’ble Supreme court was dealing with an order passed by the High Court of Jharkhand at Ranchi in a First Appeal arising out of the proceedings under the Land Acquisition Act. Reference under Section 18 of the Act was rejected and aggrieved by the same, the original claimant / land owner preferred an appeal before the High Court. He also moved an application to receive the additional evidence under Order 41, Rule 27 of CPC and while deciding the appeal, the High Court dismissed the said application. The Hon’ble Supreme Court while opining that the appellate Court should not travel outside the record of the lower court and cannot take any evidence in appeal and Order 41, Rule 27 of CPC, as an exception enables the appellate Court to take additional evidence in exceptional circumstances, that the appellate Court may permit additional evidence if the conditions laid down in the said Rule are found to exist and the parties are not entitled, as of right, to the admission of such evidence, observed that where the additional evidence sought to be adduced removes the cloud of doubt over the case and the evidence has a direct and important bearing on the main issue in the suit and interest of justice clearly renders it imperative that it may be allowed to be permitted on record, such an application may be allowed.

20) In the case on hand, as noted earlier, no application to receive the additional evidence was filed like in the connected appeal under Order 41 Rule 27(1) (aa) of CPC. Even if such an application is made, the Court is required to see whether the material sought to be received as additional evidence, could not be produced at the time of the proceedings before the Reference Court at the first instance as it was not within the knowledge of the party i.e., the appellant-State herein or that despite exercise of due diligence, the same could not be produced by it, at the time when the decree appealed against was passed. That apart, from a reading of the judgment in Sanjay Kumar Singh’s case referred to supra, no argument with reference to the power of the appellate Court under Order 41 Rule 27 (1) (aa) of CPC appears to have been addressed.

21) In Malayalam Plantations Ltd., the Hon’ble Supreme Court while setting aside the order of the High Court of Kerala, opined that when application for receipt of additional evidence under Order 41 Rule 27 of C.P.C., was filed, it was the duty of the High Court to deal with the same on merits. It also stated that under Oder 41 Rule 27, the additional evidence could be adduced in one of the three situations, viz., (a) whether the trial court has illegally refused the evidence although it ought to have been permitted (b) whether the evidence sought to be adduced by the party was not available to it despite the exercise of the due diligence; (c) whether the additional evidence was necessary in order to enable the appellate court to pronounce the judgment or any other substantial cause of similar nature. In Para No.17, the Hon’ble Apex Court held as follows:

                  ―It is equally well settled that additional evidence cannot be permitted to be adduced so as to fill in the lacunae or to patch up the weak points in the case. Adducing additional evidence is in the interest of justice. Evidence relating to subsequent happenings or events which are relevant for disposal of the appeal, however, it is not open to any party, at the stage of appeal, to make fresh allegations and call upon the other side to admit or deny the same. Any such attempt is contrary to the requirements of Order 41 Rule 27 C.P.C. Additional evidence cannot be permitted at the appellate stage in order to enable other party to remove certain lacunae present in that case.‖

22) In Shalimar Chemical Works Ltd., referred to supra, the Hon’ble Supreme Court was dealing with an appeal against the judgment and order of the erstwhile High Court of Andhra Pradesh at Hyderabad, examining the matter with reference to Order 41 Rule 27(1)(b) of C.P.C., the Hon’ble Supreme Court set aside the order passed by the Division Bench.

                  Be that as it may.

23) In State of Karnataka and Another v. K.C.Subramanya and Others((2013) 13 SCC 468), the Hon’ble Supreme Court had an occasion to examine Order 41 Rule 27 (1) (aa) of CPC, in an appeal filed against the judgment of High Court of Karnataka. Referring to the said provision, the Hon’ble Supreme Court, dismissed the appeal inter alia holding as follows:

                  ―4………

                  On perusal of this provision, it is unambiguously clear that the party can seek liberty to produce additional evidence at the appellate stage, but the same can be permitted only if the evidence sought to be produced could not be produced at the stage of trial in spite of exercise of due diligence and that the evidence could not be produced as it was not within his knowledge and hence was fit to be produced by the appellant before the appellate forum.

                  5. It is thus clear that there are conditions precedent before allowing a party to adduce additional evidence at the stage of appeal, which specifically incorporates conditions to the effect that the party in spite of due diligence could not produce the evidence and the same cannot be allowed to be done at his leisure or sweet will.

                  6. In the instant matter, the appellants are a public authority and have sought to produce a road map which, it is unbelievable, was not within the knowledge of the appellants indicating a road to the disputed land. Therefore, the rejection of the application of the appellants to rely on the said map has rightly not been entertained at the stage of first appeal. The impugned order thus does not suffer from legal infirmity so as to interfere with the same.‖

24) In Kirpa Ram (deceased) Through Legal Representatives and Others((2021) 13 SCC 57), a three Member Bench of the Hon’ble Supreme Court was dealing with an appeal against the concurrent findings in a suit for perpetual injunction. Referring to the facts of the case and disposal of appeal by the appellate Court without passing any order on the application filed under Order 41, Rule 27 of CPC, for permission to lead additional evidence, the Hon’ble Supreme Court opined that ―once the parties have understood the said controversy and had adduced evidence before the Trial Court, the appellant cannot be permitted to produce additional evidence in the first appeal.‖

25) N.Kamalam (dead) and Another v. Ayyasamy & Another(2001 (5) Supreme 689) is a case wherein the appellant before the Hon’ble Supreme Court, suffered a decree in 1983, filed an appeal before the High Court in April, 1983. In the said appeal, an application for permission to adduce the additional evidence under Order 41 Rule 27 of CPC, was filed in August, 1993. The said application and the appeal were dismissed. The Hon’ble Supreme Court upheld the decision of the High Court inter alia opining that a plain reading of Order 41 Rule 27 would depict that rejection of the claim for production of evidence after a period of ten years from the date of filing of the appeal cannot be termed to be erroneous or an illegal exercise of discretion. In the said judgment, the Hon’ble Apex Court opined that the provisions of Order 41 Rule 27 of CPC, has not been engrafted in the Code so as to patch up the weak points in the case and to fill up the omissions in the Court of Appeal. It does not authorize any lacuna or gaps in evidence to be filled up.

26) In the light of the judgments referred to above, even if any such an application is filed, no relief can be granted unless the requirements are satisfied.

27) Even assuming that the material is required to enable the Court to render complete justice, at this length of time, in the considered opinion of this Court, no useful purpose would be served as the subject matter structures of the respondents / claimants were acquired pursuant to the Notification issued on 01.05.2007 i.e., more than 18 years ago. The Reference Court passed the order and decree under appeal on 22.09.2014, more than a decade ago. It is not known as to whether the officers who prepared the estimates on behalf of the Irrigation and Power Department are still in service and available for examination. The submission to remand the matter causes more injustice to the respondents / claimants, who lost their property and yet, not received the compensation. Be that as it may. After considering the submissions made by the learned Special Government Pleader for the appellant, this Court is of the considered opinion that the appellant had not made out a case for remand. Point No.2 is answered accordingly against the appellant.

Point No.1

28) It is the contention of the learned Special Government Pleader that the compensation as enhanced by the Reference Court is without any valid basis and highly excessive.

29) To substantiate their claim for enhancement, the respondents as mentioned supra, examined P.Ws.1 to 3 and got marked Exs.A1-Abstract estimates and Ex.A2-Certified copy of the Judgment in L.A.O.P.No.891 of 1999 dated 25.02.2002. On behalf of the Referring Officer, R.W.1 i.e., the Special Collector was examined and Ex.B1-Award was got marked.

30) As per the judgment of Hon’ble Supreme Court in Chimanlal Hargovinddas v. Spl.Land Acquisition Officer, Poona (1988 (3) SCC 751)], mere marking of Ex.B1-Award in the absence of oral and documentary evidence supporting the fixation of market value by the Land Acquisition Officer would not enure to the benefit of the State. Be that as it may.

31) It is trite Law that the claimant has to prove its claim and this Court in the absence of any evidence on behalf of the appellant, has no option except to look into the evidence adduced by the respondents / claimants. In support of the case of the respondents, claimant No.1 was examined as P.W.1. In his affidavit filed in lieu of chief examination, he stated that the LAO, failed to estimate the cost of material like wood, steel etc., and transportation charges for construction material, failed to take the assistance of R & B Engineers for preparing estimates. In cross examination, he denied that the durability of the wood is only 15 years and that the construction material like sand or steel are available in their village itself. He denied the suggestion that the construction material was not transported from a distant place of 70 Kms., from their village. He further denied the suggestion that Ex.A1 estimation was not correct. Nothing much was elicited in the cross examination of the said witness (P.W.1), except making the said suggestions. P.W.2., who was a licensed Civil Engineer in his chief affidavit stated that he prepared 347 estimations covering all varieties of constructions and that he visited the Gundavolu Village and found the value of the structures 2 to 3 times over and above the value fixed by the LAO and that he prepared the estimations basing on the SSR rates of 2007-2008. He also deposed that since 20 years he is doing estimations and constructions works to private persons as Licensed Civil Engineer. P.W.2 denied the suggestion that he was not competent to assess the value of the structures and that the estimations are not correct. Nothing was elicited in the cross examination of P.W.2, much less with regard to the correctness or otherwise of the estimates prepared by him.

32) P.W.3, who was a resident of neighbouring village i.e., Rekalagunta in his evidence stated that his lands and structures were acquired for the purpose of construction of Somasila Project under Teluguganga Project and as the compensation awarded was low, an application under Section 18 of the Act was filed and the learned Reference Court, after due examination of the matter, enhanced the market value by 100% in L.A.O.P.No.891 of 1999 (Ex.A2 dated 25.02.2002). Nothing much was elicited in the cross examination, even in respect of the said witness.

33) Under the said circumstances, the contention that the order under appeal is without any valid basis, cannot be accepted. However, it is pertinent to note that the learned Reference Court while disposing of the O.P., enhanced the market value of the structures per sq. mtr., by 150% over and above the market value fixed by the Land Acquisition Officer, without assigning specific reasons. Even if the evidence of P.W.2 is taken into account, the value of the structures could be two to three times more over and above the value fixed by the Land Acquisition Officer. Therefore, in the considered opinion of this Court, the fixation of Market Value of the structures in terms of Ex.A2 i.e., 100% over and above the market value fixed by the Land Acquisition Officer would be just and reasonable. Accordingly, the point No.1 is answered.

34) In the result, the appeal is allowed in part, by reducing the market value of the subject matter structures from 150% per sq. mtr., to 100% over and above the market value fixed by the Land Acquisition Officer. Rest of the order under appeal stands confirmed. No costs.

                  As a sequel, miscellaneous applications if any, pending shall stand closed.

 
  CDJLawJournal