1. This petition is filed seeking the following reliefs :-
"a. Issue an appropriate writ, order or direction, quashing the common public notice/Aam Soochna issued by the Madhya Pradesh Grih Nirman Evam Adhosanrachna Vikas Mandal concerning vacation and proposed demolition of EWS Janata Prakoshth buildings (Annexure P/3), to the extent it affects the petitioner's residential premises.
b. Issue an appropriate writ, order or direction, in the nature of Prohibition, prohibiting and restraining the respondents, their officers, agents and employees from interfering with the peaceful residence and occupation of the Petitioner and his family members in the residential premises, or from demolishing the same or dispossessing them, except by following due process of law and the mandatory statutory procedure.
c. Issue any other appropriate writ, order or direction, including grant of costs of the petition, which this Hon'ble Court may deem just and proper in the facts and circumstances of the case."
2. The matter came up for consideration before this Court on 22.11.2026. This Court has passed the following orders :-
"This petition is filed seeking an interim protection with respect to demolition drive carried out jointly by the Housing Board i.e. respondent No.2 and the Municipal Corporation, Bhopal i.e. respondent No.4 with respect to the premises in question on the ground that the premises in question is in a dilapidated condition. The construction of premises in question was raised way back in the year 1986.
It is informed by the counsel appearing for respondents No.2 & 3/Housing Board that under the project of the Housing Board, there are 600 Janta Quarters which were constructed, out of which they could only allot 110 to the allottees and the rest of the quarters are encroached and despite several efforts made by them, the encroachers could not be evicted. A report is submitted by the Municipal Corporation, Bhopal along with the photographs in this petition to demonstrate that the houses are in dilapidated condition and for demolition of the entire building, action was initiated by issuance of notices since the year 2016. It is submitted that the respondents have issued regular notices with respect to demolition of property and also arranged camps and explain the same to the residents of that area.
It is argued that the proposal is floated by the Housing Board for reconstruction of the entire houses and the proposal is also given to the legal allottees that the extra construction of 20% will be granted to them in addition to what has been occupied by them.
It is further pointed out by the counsel appearing for the Housing Board that they are offering the rent for the alternative accommodation till the project is completed and the possession is handed over to them. A specific query was raised to the counsel that how much is the rent which is offered by the Housing Board, he fairly submits that whatever rent is fixed by the Collector according to the area in question & the scheme, the same will be given by the Housing Board.
Counsel appearing for the petitioner submits that the Collector is offering a rent of Rs.1200/- to 1500/- which is much less than what is currently prevailing in the relevant area.
Petitioner's counsel further submits that they will seek instructions from the petitioner with respect to the proposal floated by the respondents and to take a final decision and communicate the outcome by next date of hearing. for which some time be granted to them. It is pointed out that demolition drive is to take place tomorrow; therefore, some interim protection be provided to the petitioner.
Counsel appearing for the respondents submits that all procedure is in line with respect to the demolition of the property, even the police protection is provided for tomorrow. However, the State counsel has made a statement that whenever required, police protection will be provided to the respondents.
Petitioner's counsel submits that let the rent be finalised by the Collector and then only demolition of petitioner's property to take place.
The respondents are agreeable to the aforesaid proposal and submit that they will initiate the demolition proceedings tomorrow but as far as petitioner's house is concerned, they will have a meeting with the petitioner as well as with the Collector to finalise the rent and to communicate the same to the petitioner. The rent in question will be identical to the premises which is occupied by the petitioner. They pray for listing of the matter on Wednesday.
In terms of the statements made before this Court as well as looking to the facts and circumstances of the case, as a matter of interim protection, no demolition to take place with respect to the quarter possessed by the petitioner i.e. EWS 465 till the next date of hearing. List the matter on 25.11.2026 for consideration."
3. In pursuance to the same, except the quarter no. 465, which is the house of the petitioner, all other 599 quarters have been demolished. Only the petitioner's quarter remains to be demolished. It is submitted that it is in dilapidated condition. The competent authority i.e. the Collector have duly fixed the rent of the premises of the petitioner @ Rs.1400/- per month.
4. Counsel appearing for the Housing Board submits that the area occupied by the petitioner is only 167 sq. ft., and the rent finalized by the Collector considering the size of the area is justified. If the petitioner has any grievance regarding the quantum of rent fixed by the Collector, he has the remedy to challenge the same before the higher authorities.
5. The counsel appearing for the petitioner submits that some breathing time be granted to enable him to shift into rented premises.
6. The fact remains that out of 600 quarters, 599 have already been demolished, and only the petitioner's quarter remains. The petitioner cannot be permitted to stay on the premises because all adjoining properties have been demolished, making it dangerous for the petitioner to remain there any longer. Therefore, a query was put to the State counsel as to whether an alternative arrangement could be made for a period of 7 to 10 days to enable the petitioner to find a rented premises for himself.
7. State counsel submits before this Court that, as other homeless persons have been accommodated in a Rain Basera (night shelter), the petitioner can also be provided accommodation there for a period of 7 days to enable him to search for rented premises.
8. The petitioner is agreeable to the aforementioned proposition of seven days, taking into account the statement made by the State counsel and the fact that the competent authority has fixed a monthly rent of Rs.1400/- to be paid to the petitioner. The counsel appearing for the Housing Board has stated that they have no objection to this arrangement and that it will be implemented forthwith. Furthermore, considering that all other nearby residential accommodations were in a dilapidated condition and have already been demolished, this Court deems it appropriate to dispose of this petition by directing the State authorities to permit the petitioner to stay in the Rain Basera for a period of seven days from today, as provided to all other homeless persons, and to ensure that the rent fixed by the Collector is paid to him. During this seven-day period, the petitioner may search for alternative accommodation and shift his belongings to the new premises.
9. As far as the demolition is concerned, as demolition has already been carried out to a large extent demolishing 599 quarters, only the quarter of the petitioner remains to be demolished, they are permitted to carry out further demolition proceedings as far as the petitioner's accommodation is concerned.
10. With the aforesaid, the petition stands disposed of.